Progress of the Third Interim Stage and Achieved Results

During the implementation of Project No. 5.1.1.2.i.0/1/22/A/CFLA/006, the necessary measurements and data analysis for the wood drying process have been carried out. Based on the collected data, the required calculations have been completed, resulting in the following achievements:

  • The electrical control and automation distribution panel for the heat recovery system has been installed and connected. It is currently being tested together with the kiln and heat recovery control software.
  • Control software for the drying kilns and the heat recovery system has been developed. The software is being tested under real operating conditions and continuously refined.
  • 90% of the air duct system has been installed.
  • Upon completion of the required tests, the heat recovery unit will be connected using the pre-fabricated air duct fittings.
  • The air-to-air heat exchanger for the heat recovery unit has been assembled, and testing of the unit is currently underway.
  • All procurement activities have been completed:
    • The air-to-water heat exchanger for the heat recovery system will be delivered within the next week.
    • Fans for air supply and exhaust in the drying kilns are scheduled for delivery by the end of November.